Government announces progressive solutions to restore electricity in Santa Elena from March 21

Víctor Hugo Ventura Ruiz,  Minister of Energy and Mines of the Republic of Guatemala
Víctor Hugo Ventura Ruiz, Minister of Energy and Mines of the Republic of Guatemala - Ministerio de Energía y Minas
0Comments

The government announced on March 19 that it is implementing technical measures to progressively restore the electricity supply in the province of Santa Elena. These actions include adding new generation capacity and carrying out a structural intervention, with full restoration of the system expected by the end of April. Scheduled power outages in the province are set to be suspended starting March 21 as these solutions come into effect.

Officials said that this week, an additional 15 megawatts (MW) will be integrated into the system—3 MW in Chanduy and 12 MW in Pechiche. Another 7 MW will come from a transformer relocated from Ibarra, bringing the short-term operational total to 22 MW.

In addition, another 6 MW is expected to arrive in the country on March 22. The equipment will be moved from customs on March 23 and installed in La Libertad canton on March 24. After installation and an estimated five days for commissioning, officials expect a total of 28 MW available by the end of March.

These steps are intended to reduce interruptions for residents across several sectors of Santa Elena, improving service continuity while work continues on a permanent solution.

A longer-term fix involves moving a large transformer with a capacity of 224 MVA from Pascuales substation to Santa Elena. Between March 15 and March 17, technical inspections were carried out on thirty-seven bridges along the route by teams from the Ministry of Transport and Public Works, Ministry of Energy, CELEC, and private companies using specialized equipment and drones. Specific points needing technical interventions were identified to ensure safe transport.

Once all necessary authorizations are granted, officials estimate that moving the transformer will take about two days. With continuous work after arrival, it is expected to become operational within approximately thirty days—restoring full capacity for Santa Elena’s electrical system by late April.



Related

Roberto Luque Nuques Director at Ministerio de Transporte y Obras Públicas

Ecuador declares emergency on Cuenca–Girón–Pasaje road after landslides block traffic

The Ecuadorian government has declared an emergency for part of the Cuenca-Girón-Pasaje road after severe landslides blocked traffic. Authorities are mobilizing resources to clear debris and restore safe passage between Azuay and El Oro.

Inés Manzano Díaz Director at Ministerio de Energía y Minas

President Daniel Noboa strengthens electrical infrastructure in Naranjal, benefiting over 610 residents

More than 610 residents in Naranjal now benefit from improved electrical infrastructure following government investment. Officials say the upgrades will enhance safety and support local development.

Inés Manzano Díaz Director at Ministerio de Energía y Minas

Government formalizes Gonzanamá and Sanguillín water protection areas in southern Ecuador

The Ministry of Environment and Energy has designated over 7,300 hectares as new Water Protection Areas in southern Ecuador’s Gonzanamá and Sanguillín cantons. Officials say this move aims to safeguard local ecosystems while ensuring reliable access to clean water for thousands. Additional infrastructure investments were also announced.

Trending

The Weekly Newsletter

Sign-up for the Weekly Newsletter from Ecuador Bulletin.